tedtalk.ai

tedtalk.aitedtalk.aitedtalk.ai

tedtalk.ai

tedtalk.aitedtalk.aitedtalk.ai
  • Time I
  • Time II
  • Time III
  • Time IV
  • About Ted
  • Proposal
  • Proposal Added Incentive
  • Additional Timestamps
  • More
    • Time I
    • Time II
    • Time III
    • Time IV
    • About Ted
    • Proposal
    • Proposal Added Incentive
    • Additional Timestamps
  • Sign In
  • Create Account

  • My Account
  • Signed in as:

  • filler@godaddy.com


  • My Account
  • Sign out

Signed in as:

filler@godaddy.com

  • Time I
  • Time II
  • Time III
  • Time IV
  • About Ted
  • Proposal
  • Proposal Added Incentive
  • Additional Timestamps

Account

  • My Account
  • Sign out

  • Sign In
  • My Account

The Republic - Austin, TX - December 5, 2022 @ 10:29-10:30 AM - EAST

1/4

The Republic - Austin, TX - December 5, 2022 @ 2:54-2:56 PM - EAST

1/6

The Republic - Austin, TX - December 6, 2022 @ 12:26 PM - EAST

1/4

Very little progress in a day under intense focus

Floors are built in 4-7 days and parking levels are built in the same time to upwards of 14 work days.


Relatively speaking, not much progress has occured since the forms in the far left corner started being put in place on December 1, 2022. The shear wall and ramp were formed and poured before the middle of November, 2022 and the ground pad and colums were poured prior to November, 2022 


After observing from this new vantage point, let alone directly on the ground on any other day, a reasonable question is how much construction progress can be expected in a single day even when all materials are at hand?


What can be observed is that building a highrise condominium and skyscraper construction is essentially hand craftsmanship aided by a crane to move and position objects of immense weight. 


Cranes: Assembling intricate parts - slowly

Pictured Right: A section of shear wall rebar is being assembled and tweaked with the aid of a crane suspending it.

With the segment off the ground, workers can manipulate the bottom of the section to ensure its constructed to specifications.

Just this one segment and stage of rebar assembly required over half an hour of the crane's time - or 1/16th of the workday. 


More of the same deliberation is needed when the segment must be hoisted on the site and then tied into position. 


Most projects commence with only 1 crane and the preponderance of projects that start with 2-3 actually complete the bulk of floors with just 1 crane. 

The Republic - Austin, TX - December 7, 2022 @ 8:13 AM - EAST (Video Captures)

1/4

The Republic - Austin, TX - December 8, 2022 @ 5:09 PM - EAST (Far Left Corner Poured)

1/4

Approximately 3,500 sqft in 8 Days

With colums and shear wall in place in place, it took 8 days to form and pour a very small area. 

The Republic - Austin, TX - December 9, 2022 @ 7:32-7:33 AM - EAST

1/4

The Republic - Austin, TX - December 10, 2022 @ 8:46-8:47 AM - EAST (Rebar for columns in far left section being built)

1/4

The Republic - Austin, TX - December 10, 2022 @ 4:21 PM - EAST

1/4

The Republic - Austin, TX - December 12, 2022 @ 8:28-8:29 AM - EAST (Rebar completed in far left section)

1/4

The Republic - Austin, TX - December 13, 2022 @ 8:28-8:29 AM - EAST (Rebar completed in far left section)

1/4

The Republic - Austin, TX - December 15, 2022 @ 8:44 AM - EAST (Concrete being poured)

1/4

6 weeks to build and pour half a floor

On December 15, 2022 a large portion of the floor still hadn't even been framed

Show More

Serious work to start building the 2nd floor was underway on January 12, 2023

1/4

The ATX Tower was in the same general position as The Rebuplic on November 8, 2022

Below is The Republic on November 7, 2022 Facing EAST

By December 10, 2022 the ATX Tower is on its 3rd Floor

Anamoly Observed

 In just 33 days, one project:


  1. Finished forming its 1st above-grade parking level.
  2. Built its 1st above-grade parking level.
  3. Formed and built its 2nd above-grade parking level.
  4. Formed its 3rd above-grade parking level.


In 33 days, a project just down the street had:


  1. About 1/2 of its 1st above-grade parking level formed.
  2. Approximately 3,500 sq. ft. of the 1st above-grade parking level poured.

Conclusion

 

The ATX Tower was heavily photographed on one day, i.e., November 8, 2022.


It broke ground on March 15, 2022, to complete shoring, excavation, 2 sub-levels, 11 above-grade levels of parking, and 47 mixed-use above-grade levels by July 23, 2024.


The Republic was heavily photographed from November 2022–January 2023.


It broke ground on June 15 and had shoring drills in place by July 1, 2022, or sooner, and did not require serious shoring or excavation. 


It completed 15 levels of parking and 29 mixed-use levels by November 20, 2024.


It appeared as though direct observation put The Republic off a normal construction timeline during the period of time direct observation was undertaken.

Copyright © 2026 tedtalk.ai - All Rights Reserved.

This website attempts to measure the traffic it generates.

Cookies are deployed soley to analyze total visits. Your personal data is not collected and sold. Declining simply prevents your visit from being counted.

DeclineAccept