Pictured Above: The Republic on August 26, 2022.
Three (3) cranes had been set up at this point in time. Work started here in early June with the removal of asphalt, caisson and pier work and crane erection.
Foundational work for the core is well under way.
1/6

Pictured Right: A worker is completeing rebar work on the far left column.

Pictured Right: Rebar work for ground level of the core is being finished with forms in place.

Pictured Right: Spanning to the far right (SW), some columns have been poured with their forms removed.
1/2
Pictured Above: A worker is now assembling the far left column's forms; the column is highlighted in pink in North facing photos on November 15, 2015.
The sliding photos pictured below, spanning center and right, show no considerable change.
1/4